What Knoxville's airport is building
A record 3.63 million passengers used a terminal built for about 2.6 million. Here is every Flight Plan milestone, and what each one changes for you.
Photo: Jackmcafee, CC BY-SA 3.0 / Wikimedia Commons
Short answer
McGhee Tyson's Flight Plan is a decade-long program. Now underway: a $186 million, 3,500-space garage due summer 2027, a 13th gate (opened fall 2026), and a security checkpoint expansion backed by a $10 million federal grant. The airport's terminal-area plan adds six more gates by 2030 and expands ticketing, baggage and screening by 2035.
Interactive
The timeline
8 milestones
- Ground broken; Flight Plan launched Done
The airport authority broke ground on the Parking Garage Expansion and Terminal Roadway Improvement Project and announced Flight Plan, a decade-long program adding gates and concessions and renovating restrooms and the checkpoint.
For travelers: Construction around the garage and roadways begins. - $10 million for the checkpoint Done
TYS was selected for $10 million from the final round of the FY2026 Airport Terminal Program to expand its security checkpoint.
For travelers: Funding secured for more screening capacity. - Lower-level lane closes Underway
The left lane on the lower-level roadway closest to the garage closes through spring 2027 for the garage canopy. It reopens for peak holiday periods.
For travelers: No curb parking on the lower level; allow extra time at pickup. - Gate 13 and new gate numbers Done
A thirteenth gate is added and gates 7 to 13 are renumbered in three weekly phases.
For travelers: Check your gate on the board or app; old numbers may not match. - Checkpoint construction starts Underway
The airport said construction on the checkpoint expansion begins this fall. Local reporting said completion is likely in 2028.
For travelers: Expect construction near security until the project finishes. - New garage opens Planned
A $186 million, six-level garage adds 3,500 spaces, with one floor for rental car operations.
For travelers: Many more covered spaces next to the terminal. - Phase 1: six more gates Planned
The terminal-area plan expands the "Y" concourse by six gates, rebuilds the apron and relocates support facilities.
For travelers: More gates for more airlines and bigger planes. - Phase 2: the core of the terminal Planned
Expanded ticketing, baggage handling and checkpoint, utility upgrades and a Taxiway A relocation.
For travelers: A larger front door for a busier airport.
Scale
By the numbers
The case
Why it matters for a Pittsburgh nonstop
The airport's own forecast in its Environmental Assessment is 4.1 million passengers by 2027 and 4.7 million by 2030, and the plan cites airlines moving from regional jets to larger narrow-body planes. More gates and a bigger checkpoint are what let a new route fit. The missing piece is evidence of demand, and that is what the pledge provides.
Questions
What is McGhee Tyson Airport building?
When will the new parking garage at TYS be finished?
Why is Knoxville's airport expanding?
Does the expansion mean new routes?
Sources
- McGhee Tyson Airport: introducing Flight Plan (Nov 7, 2024)
- TYS Flight Plan program site
- McGhee Tyson Airport: seen at TYS this summer (June 1, 2026)
- McGhee Tyson Airport: $10 million for security checkpoint expansion (June 2026)
- WVLT: McGhee Tyson Airport receives $10 million grant to expand security checkpoint (June 9, 2026)
- McGhee Tyson Airport: a new gate coming to TYS (Sept 21, 2026)
- McGhee Tyson Airport: temporary lane closure, lower level
- McGhee Tyson Airport: Environmental Assessment for the Terminal Area Development Program
- McGhee Tyson Airport: reflecting on a record year for air service